Notice to Mariners
NOTM 016a/02: Commissioning Delay of Sealand Light
6 February 2002
The Principality is grateful for the comments concerning the commissioning of
this navigational aid received during the formal consultative period from July
to December of 2001.
Exceptionally, belated comments have now been received from a neighbouring
State a month after the closure of that consultative period. The Principality
considers it important to consider these comments. In that connection, the
final commissioning of Sealand Light has been temporarily suspended during a
further exceptional consultative period of 60 days.
Comments should be directed to the Bureau of Internal Affairs (burint@sealandgov.org),
SEALAND 1001, Sealand Post Bag, IP11 9SZ, UK.